October 4, 2018 Since my last report most of the crew was routinely transforming our work site into an exhibition area for Saturday’s open house. The final site clean up was completed along with pre-staging of tables, chairs and tarps for shade. The engine and tender received a good pressure washing and polish with the […]

TW3

October 4, 2018

Work Session Status Week Ending 09/29/2018

September 24, 2018 Hello Steamers! Madame Secretary and I are back from our nearly two weeks of R&R. Thanks to all who continued on in our absence. This week, other than the usual work details, we began prepping the site for the Annual Open House this coming Saturday. Everyone in the near Albuquerque area continue […]

TW3

September 24, 2018

Work Session Status Week Ending 09/22/2018

August 27, 2018 Besides finishing the pit rebuild, getting the speeder up and running, rejoining the locomotive and tender and outfitting the new souvenir store, we had a bit of an official first steam-up! Wednesday, on our regular work day, volunteers came in early to prepare for a live television steam-up with Channel 4’s Weatherman […]

TW3

August 27, 2018

Work Session Status Week Ending 08/25/2018

August 15, 2018 The last of the welding was completed on the pit repair. The locomotive rolled over it and all was quiet again. After a bit of air brake testing she was rolled back over the pit in preparation of reconnecting the 2926 to her tender. They were reconnected along with the water and […]

TW3

August 15, 2018

Work Session Status Week Ending 08/11/2018

August 7, 2018 We’ve had a couple of busy weeks. Our forge masters have been turning out brass replicas of the 2926 tender plates. They have sold up through #8 so far. If you want one you better get your slot nailed down. Contact us through the web site link at www.2926.us. They are $100 […]

TW3

August 7, 2018

Work Session Status Week Ending 08/04/2018

July 25, 2018 Hello everyone. I wanted to bring everyone up to date with the on site activities. The pit repair is still a few weeks away from completion. We need to adjust the main 14′ H beam rail support so it will center over the vertical structural steel supports. The aftermath heat here has […]

TW3

July 25, 2018

Work Session Status Week Ending 07/14/2018

June 23, 2018 Much has taken place since my last work report as I was waiting to provide some good news. The summer solstice has come and gone, the days will be getting shorter and lower temperatures. Yeah, right! Most of you are aware of the locomotive’s rear truck derailing as it passed over the […]

TW3

June 23, 2018

Work Session Status Week Ending 06/23/2018

June 5, 2018 For the past few weeks we have been preparing the engine for it’s first steam-up since the early 1950’s. We were able to achieve a full boiler hydro except for some very minor leaks which we addressed last week. The usual jacketing work continues making templates and check fitting the fabricated sheets. […]

TW3

June 5, 2018

Work Session Status Week Ending 06/02/2018

May 21, 2018 This week we concentrated finishing up repairing the various leaking old fittings and valves so their seats were lapped to a shinny new surface. The casting crew began a new project by fabricating the mold for a new cab light box cover. The pour was made so now the machine work begins […]

TW3

May 21, 2018

Work Session Status Week Ending 05/19/2018

May 9, 2018 Projects this week concentrated on preparing the engine for it’s next full hydro by fixing small leaks and making repairs to the flue sandbox. As usual we made more paper templates for the jacketing fabricators, picking up those fabricated parts, checking for proper fit then on to the paint shop. When complete […]

TW3

May 9, 2018

Work Session Status Week Ending 05/05/2018